14   Payment schedules

(1)   A person on whom a payment claim is served (the respondent ) may reply to the claim by providing a payment schedule to the claimant.

(2)   A payment schedule:

(a)    must identify the payment claim to which it relates, and

(b)   must indicate the amount of the payment (if any) that the respondent proposes to make (the scheduled amount ).

(3)   If the scheduled amount is less than the claimed amount, the schedule must indicate why the scheduled amount is less and (if it is less because the respondent is withholding payment for any reason) the respondent's reasons for withholding payment.

(4)   If:

(a)    a claimant serves a payment claim on a respondent, and

(b)   the respondent does not provide a payment schedule to the claimant:

(i)            within the time required by the relevant construction contract, or

(ii)          within 10 business days after the payment claim is served,

whichever time expires earlier,

the respondent becomes liable to pay the claimed amount to the claimant on the due date for the progress payment to which the payment claim relates.

 


 

Perform (NSW) Pty Ltd v MEV-AUS Pty Ltd & Anor [2009] NSWCA 157: Giles JA McColl JA Young JA
KEY ISSUE: payment schedule could "indicate" reasons for nil valuation by referring to previous payment schedule - in any event adjudicator's view that it could not did not make adjudication void - what is indicated in a payment schedule is for adjudicator to determine - did not fail to comply with basic and essential requirements of valid adjudication - reliance on back charge claims as set-off payment schedule could "indicate" reasons for nil valuation by referring to previous payment schedule - in any event adjudicator's view that it could not did not make adjudication void - what is indicated in a payment schedule is for adjudicator to determine

Thiess Pty Ltd & Anor v Lane Cove Tunnel Nominee Company Pty Ltd & Anor [2009] NSWCA 53: Giles JA Tobias JA Handley AJA
KEY ISSUE: payment schedule - whether contract required a time for provision of payment schedule - contractual payment schedule replied to contractual progress payment claim - not to statutory payment claim - stated time was not for provision of statutory payment schedule

Baulderstone Hornibrook Pty Ltd v Queensland Investment Corporation [2007] NSWCA 9: Giles JA Tobias JA Basten JA
KEY ISSUE: whether a payment schedule is properly provided if it is not referred to in a cover letter — whether a payment schedule prepared and signed by an agent without express authority can be said to have been provided by the principal

Falgat Constructions Pty Limited v Equity Australia Corporation Pty Limited [2006] NSWCA 259: Handley JA Hodgson JA Hunt AJA
KEY ISSUE: Time limit for provision of payment schedules - Whether adjudication application can be made if payment schedule provided outside the time limit - Whether s.109X of the Corporations Act 2001 (Cth) applies to provision of payment schedule to a corporation - Effect of s.29 of the Acts Interpretation Act 1901 (Cth) - Whether "provide" means anything different from "serve" in the Act, and is governed by s.31 of that Act.

Springs Golf Club Pty Ltd v Profile Golf Pty Ltd [2006] NSWSC 344: Rein AJ
KEY ISSUE: what constitutes a valid payment schedule under the Act

Acclaim Building Management Pty Ltd v Loewenthal [2006] NSWDC 29: Johnstone DCJ
KEY ISSUE: what constitutes an “indication” of the amount payable in a payment schedule?

Lucas Stuart Pty Limited v Council of the City of Sydney [2005] NSWSC 840: Einstein J
KEY ISSUE: Plaintiff builder and defendant local government council-Builder serves payment claim on council-Council fails to serve a payment schedule on builder within specified time-Builder seeks summary judgment-Council claims payment claim served in context of misleading and deceptive conduct-Council claims builder estopped from relying on payment claim-No arguable case-Summary judgment awarded

Tooma v Eaton [2002] NSWSC 514 (11 June 2002): Master Macready
KEY ISSUE: whether absence of a payment schedule under s 14 of the Act meant that there was no genuine dispute to a statutory demand based on a payment claim made under s 13 of the Act

Fyntray Constructions Pty Ltd v Macind Drainage & Hydraulic Services Pty Ltd [2002] NSWCA 238 (26 July 2002): Heydon JA, Hodgson JA, Ipp AJA
KEY ISSUES: whether a payment claim could be made even though the claim relates to work done in periods prior to the month in which the payment claim is served – whether payment claim could include entitlements to more than one progress payment

Paynter Dixon Constructions Pty Limited v JF & CG Tilston Pty Limited and Anor [2003] NSWSC 869 (25 September 2003): Bergin J
KEY ISSUES: whether adjudicator validly appointed – whether adjudicator has jurisdiction to determine a dispute in relation to a payment claim that included a contentious claim for damages or loss of profits for alleged wrongful repudiation of a contract

Leighton Contractors Pty Limited v Campbelltown Catholic Club Limited, Campbelltown Catholic Club Limited v Leighton Contractors Pty Limited [2003] NSWSC 1103 (3 December 2003) : Einstein J
KEY ISSUES: whether summary judgment in respect of a payment claim under the Act should be entered – whether payment claim was a valid payment claim within s 13(2) – whether the Architect’s certificate constituted the service of a payment schedule

Multiplex Constructions Pty Ltd v Luikens and Anor [2003] NSWSC 1140 (4 December 2003): Palmer J
KEY ISSUES: whether the determination of an adjudicator is open to judicial review – whether an adjudication may be reviewed for error law on the face of the record – what must be disclosed by a payment schedule – whether adjudicator must assess value by inspection - whether whole determination must be quashed

John Holland Pty Limited v Cardno MBK (NSW) Pty Limited & Ors [2004] NSWSC 258 (20 April 2004): Einstein J
KEY ISSUES: whether adjudication application should be relevantly tied to the payment claim [such that the adjudication application cannot include reasons supporting the payment claim unless those reasons had been included in the payment claim

Barclay Mowlem Construction v Tesrol Walsh Bay [2004] NSWSC 716 (13 August 2004): McDougall J
KEY ISSUES: whether defendant has arguable defence to preclude plaintiff from obtaining summary judgment where document alleged to be payment schedule did not indicate the payment defendant intended to make – whether defendant provided payment schedule for purposes of s14 – whether question to be determined on final hearing and not by way of summary judgment – whether defendant relied upon representation to its detriment by taking no further steps under Act in respect of payment claim – whether estoppel defence prohibited by s34 – whether question to be resolved on application for summary judgment

Estate Property Holdings Pty. Limited v. Barclay Mowlem Construction Limited [2004] NSWCA 393 (3 November 2004) : Mason P, Giles JA, Hodgson JA
KEY ISSUES: whether construction work is the work required by the contract, the work for which payment is claimed or each item of work for which payment is claimed

Property & Equity Developments v Parnell [2004] NSWSC 1035 (12 November 2004): Campbell J
KEY ISSUES: whether payment claim comprising 4 invoices valid

Barclay Mowlem v Tesrol Walsh Bay [2004] NSWSC 1232 (9 December 2004): McDougall J
KEY ISSUES: whether letter in law sufficient to be payment schedule – whether “nothing” an amount for purposes of s14(2)(b) – whether letter “provided” within meaning of s14(1)

Isis Projects v Clarence Street [2004] NSWSC 714 (13 August 2004): McDougall J
KEY ISSUES: whether plaintiff entitled to recover amounts unpaid as a debt – whether progress claims identified work by single line item references – whether progress claims supported by sufficient evidence

Coordinated Construction Co v J M Hargreaves & Ors [2005] NSWSC 77 (22 February 2005): McDougall J
KEY ISSUES: whether determination void because adjudicated amount included amounts assumed (but not decided) not to be “for” construction work

 

<<

TOC

>>