15    Consequences of not paying claimant where no payment schedule

(1)   This section applies if the respondent:

(a)    becomes liable to pay the claimed amount to the claimant under section 14 (4) as a consequence of having failed to provide a payment schedule to the claimant within the time allowed by that section, and

(b)   fails to pay the whole or any part of the claimed amount on or before the due date for the progress payment to which the payment claim relates.

(2)   In those circumstances, the claimant:

(a)    may:

(i)                  recover the unpaid portion of the claimed amount from the respondent, as a debt due to the claimant, in any court of competent jurisdiction, or

(ii)                make an adjudication application under section 17 (1) (b) in relation to the payment claim, and

(b)   may serve notice on the respondent of the claimant's intention to suspend carrying out construction work (or to suspend supplying related goods and services) under the construction contract.

(3)   A notice referred to in subsection (2) (b) must state that it is made under this Act.

(4)   If the claimant commences proceedings under subsection (2) (a) (i) to recover the unpaid portion of the claimed amount from the respondent as a debt:

(a)    judgment in favour of the claimant is not to be given unless the court is satisfied of the existence of the circumstances referred to in subsection (1), and

(b)   the respondent is not, in those proceedings, entitled:

(i)            to bring any cross-claim against the claimant, or

(ii)          to raise any defence in relation to matters arising under the

construction contract.

 


 

Dualcorp Pty Ltd v Remo Constructions Pty Ltd [2009] NSWCA 69: Allsop J & Macfarlan JA & Handley AJA
KEY ISSUE: claimant seeking summary judgment for a payment claim where there is no payment schedule – but a same payment claim has been made and adjudicated before – refuse to enter summary judgment

Project Architecture Pty Limited v Peter's of Kensington Pty Limited [2008] NSWDC 24: Rolfe DCJ
KEY ISSUE: claim under Act - Application for Summary Judgment - Relevant principles - Whether triable issue of fact or law had been disclosed - Whether party raising triable issue of fact required to cross-examine opposing party

Majeed v Mahmud and 4 Ors [2007] NSWSC 1413: Brereton J
KEY ISSUE: Security of Payment – where no payment schedule – disallowance of amounts apparently not in respect of construction work or related services

Kell and Rigby Pty Limited v Guardian International Properties Pty Ltd [2007] NSWSC 554: Bergin J
KEY ISSUE: consequence of failure to provide a notice under s 17(2) of the Act before filing adjudication application - whether filing adjudication application without providing notice under s 17(2) of the Act amounts to an election under s 15(2)(a)(ii) of the Act - whether the plaintiff is precluded from bringing proceedings

Rojo Building Pty Limited v Jillcris Pty Limited [2007] NSWSC 880: McDougall J
KEY ISSUE: Payment claim served on defendant - Failure of defendant to provide payment schedule within time limited by the Act - Plaintiff serves notice of intention to make adjudication application - Whether plaintiff thereby made any election - Whether open to plaintiff to withdraw any election made

Bitannia Pty Ltd & v Parkline Constructions Pty Ltd [2006] NSWCA 238: Hodgson JA Tobias JA Basten JA
KEY ISSUE: whether a breach of s 52 of Trade Practices Act 1974 (Cth) can be relied on as a defence – whether Building Payment Act s 15(4)(b)(ii) precluded such defence

Nepean Engineering Pty Ltd v Total Process Services Pty Ltd (In Liquidation) [2005] NSWCA 409: Hodgson JA, Santow JA & Ipp JA
The Court of Appeal found that the grant of summary judgment based on s15(2)(a)(i) is final and not interlocutory

Lucas Stuart Pty Limited v Council of the City of Sydney [2005] NSWSC 840: Einstein J
KEY ISSUE: Plaintiff builder and defendant local government council-Builder serves payment claim on council-Council fails to serve a payment schedule on builder within specified time-Builder seeks summary judgment-Council claims payment claim served in context of misleading and deceptive conduct-Council claims builder estopped from relying on payment claim-No arguable case-Summary judgment awarded

Isis Projects v Clarence Street [2004] NSWSC 714 (13 August 2004): McDougall J
KEY ISSUES: whether plaintiff entitled to recover amounts unpaid as a debt – whether progress claims identified work by single line item references – whether progress claims supported by sufficient evidence

Estate Property Holdings Pty. Limited v. Barclay Mowlem Construction Limited [2004] NSWCA 393 (3 November 2004) : Mason P, Giles JA, Hodgson JA
KEY ISSUES: whether construction work is the work required by the contract, the work for which payment is claimed or each item of work for which payment is claimed

Bell Partners v Kann Finch [2004] NSWSC 1034 (8 November 2004): Master Harrison
KEY ISSUES: whether respondent entitled to a progress claim pursuant to s13 of the Act – whether progress claim effective under provisions of the Act

Property & Equity Developments v Parnell [2004] NSWSC 1035 (12 November 2004) : Campbell J
KEY ISSUES: whether payment claim comprising 4 invoices valid

Beckhaus v Brewarrina No 2 [2004] NSWSC 1160 (7 December 2004): Master Macready
KEY ISSUES: whether defendant entitled to liquidated damages under the contract in circumstances where plaintiff did not achieve practical completion – whether leave should be allowed for claim for liquidated damages – whether there was indemnity under s27 of the Act against liquidated damages claim

Aldoga Aluminium Pty Ltd v De Silva Starr Pty Ltd [2005] NSWSC 284 (1 April 2005) : Palmer J
KEY ISSUES: whether Plaintiff precluded from raising existence of contract by operation of s15(4) of the Act – whether facts demonstrated genuine dispute

Vince Schokman & Anor v Xception Construction Pty Limited and Anor [2005] NSWSC 297 (4 April 2005): Einstein J
KEY ISSUES: whether s17(2) notice of intent to apply for adjudication served out of time – whether adjudication application made out of time – whether claimant can revert to seeking judgment in curial proceedings when adjudication procedures miscarry.
Decision: Adjudication held to be void.

 

<<

TOC

>>